The Cost of Analytical Failure
On 20 April 2010 the Deepwater Horizon rig exploded in the Gulf of Mexico and eleven men died. The official record shows the warnings were on the instruments, and that the people reading them explained them away.
I spent twelve years on construction projects. Deepwater Horizon is the case I use to open What Are We Missing? because the investigation lets me examine decisions alongside the evidence available to the crew. I do not need to assume that every project failure follows the same pattern.
The rig was finishing the Macondo well. The well was in trouble. It had been budgeted at $96.2 million and 51 days, and by 20 April it was almost six weeks behind and more than $58 million over budget. [1] Six days earlier, a BP engineer had written in an e-mail that it had been a "nightmare well". [1]
The first decision was not to run the cement evaluation log. Schlumberger's team was sent home on the 11am helicopter. The Commission describes the decision as saving time and the $128,000 fee, and quotes BP Wells Team Leader John Guide saying the people on the rig were "completely satisfied" with the cementing job. That statement was not an independent measurement of the cement barrier. [2]
The second decision concerned the negative-pressure test. The first attempt to bleed drill-pipe pressure stopped at 266 psi; after closing, it rose to 1,262 psi. A second attempt reached zero, but pressure then rose to at least 773 psi. A third reached zero before pressure rose to 1,400 psi. Post-incident statements attributed a "bladder effect" explanation to Jason Anderson. Lee Lambert did not recall anyone agreeing or disagreeing. [3, p107]
The crew then tested through the kill line, where pressure was bled to zero and no flow was observed for 30 minutes. The drill pipe still showed 1,400 psi. The Commission says the readings never appear to have been reconciled and concludes that, on the available information, the drill-pipe pressure could only have been caused by a leak into the well. At 8pm the Well Site Leaders, consulting the crew, nevertheless accepted the test. [3, pp108-109]
The decision to proceed rested on a test the Commission found had been misinterpreted. I would want the unresolved pressure reading dealt with before accepting the result.
The third failure: a warning that was missed. At about 9.01 p.m., with the pumps running at a constant rate, the drill-pipe pressure began to rise. Over seven minutes it moved from 1,250 to 1,350 psi. [4] That pressure rise needed explaining before the operation continued. The first explosion occurred at approximately 9.49 p.m. Eleven men were killed. [4, p114]
What the investigation records is a skipped evaluation, a test that was misread, and warnings that did not stop the work. I can look at those decisions without claiming that each of them seemed reasonable to everyone at the time. The report gives me evidence about what happened, with limits on what can be reconstructed afterwards.
Capping the well took until 15 July 2010. [5] BP went on to plead guilty to 14 criminal counts, 11 of them for felony manslaughter. [6] The consequences ran well past the night of the explosion.
On a decision of my own, I start with the evidence that does not fit the proposed explanation. What check would settle it? Who can hold the work while the check runs? Those two questions are what I take from the case.
Chapter 1 of What Are We Missing? follows the events of that night before examining how we frame and test decisions. The book sets out PRISM and includes chapter bibliographies and numbered endnotes. Publication is planned for 13 February 2027.

Zafar Alam is a civil engineer and Chartered Construction Manager with about 12 years on major projects. He is the author of What Are We Missing? How to Think More Clearly Before You Decide, planned for 13 February 2027.
Read next
A Lesson Is Not Learned Because We Wrote It DownWriting a lesson down is not learning it. What a handover, a closed action and a review change for the next project.Nobody Writes AloneDifferent roles in editing, ghostwriting and computer-assisted writing.Notes
- National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling, Deep Water: The Gulf Oil Disaster and the Future of Offshore Drilling (2011), chapter 1 - the $96.2 million and 51-day budget, almost six weeks behind schedule and more than $58 million over budget by 20 April, and Brian Morel's 14 April e-mail calling it a "nightmare well". https://www.govinfo.gov/content/pkg/GPO-OILCOMMISSION/pdf/GPO-OILCOMMISSION.pdf
- National Commission (2011), chapter 1, printed pp. 3-4 and 102 - the 7.30 a.m. decision to send the Schlumberger cement evaluation team home on the 11.00 a.m. helicopter, "saving time and the $128,000 fee", and John Guide's "completely satisfied" statement, attributed by the Commission's chapter 1 note 22 to his testimony. Same report as note 1. https://www.govinfo.gov/content/pkg/GPO-OILCOMMISSION/pdf/GPO-OILCOMMISSION.pdf
- National Commission (2011), pp. 107-109. The first drill-pipe bleed reached 266 psi, with pressure rising to 1,262 psi after closure. Later attempts reached zero but pressure returned to at least 773 psi and then 1,400 psi. The kill-line test showed no flow for 30 minutes while the drill pipe remained at 1,400 psi. The Commission says the readings never appear to have been reconciled. https://www.govinfo.gov/content/pkg/GPO-OILCOMMISSION/pdf/GPO-OILCOMMISSION.pdf
- National Commission (2011), pp. 110, 114 - drill-pipe pressure rising from about 9.01 p.m. at a constant pump rate, from 1,250 to 1,350 psi over seven minutes. The explosion at about 9.49 p.m. is on printed p. 114. The Commission notes the data it relies on is the Sperry Sun subset, which survived the sinking, and is an approximation of what the crew saw. https://www.govinfo.gov/content/pkg/GPO-OILCOMMISSION/pdf/GPO-OILCOMMISSION.pdf
- National Commission (2011), chapter 5: the well was capped on 15 July 2010. https://www.govinfo.gov/content/pkg/GPO-OILCOMMISSION/pdf/GPO-OILCOMMISSION.pdf
- US Department of Justice, United States v. BP Exploration and Production, Inc., case 2:12-cr-00292-SSV-DEK. Historical account of 29 January 2013 plea to 14 counts including 11 felony manslaughter counts. This page also contains stale trial schedules and is not used for current case status. https://www.justice.gov/criminal/criminal-vns/case/united-states-v-bp-exploration-and-production-inc